RN No. 209
Project Name The Treasure Project
Developer Ayeyar Apex Co.,Ltd
Status under-construction
Basement -
Storey 3B + 26 Storeyed (2no.)
Building Height -
Location No(1-k), Narnattaw Str,Kamaryut.
Region
State
Project Status
Architecture 1. Presented Conceptual Architectural Presentation for Pile Load Test. 2. Presented final Architectural Presentation. (29.10.18) 3. Sent Comment to company. (5.11.18)
Structure 1. ULT Recommended. (6.7.17) 2. WLT Recommended. (13.3.17) 3. Piling Recommended. (3.7.17) 4. Sent DE comment. (22.12.17) 5. DE comment reply. (9.1.18) 6. Sent comment for DE. 7. Presented final structural Presentation. (29.10.18) 8. Sent Comment to company. (6.11.18) 9. DE Recommended. (26.12.2018)
Electrical 1. Company submit reasons for the delay (14.1.2019). 2. Not yet submitted by developer.
ACMV 1. Company submit reasons for the delay (14.1.2019). 2. Not yet submitted by developer.
Water and Sanitation 1. Company submit reasons for the delay (14.1.2019). 2. Not yet submitted by developer.